Location: Elkton Road, MD state line to Gravenor Lane
3:00 p.m. on Sunday, August 29, 2021 until 7:00 p.m. on Sunday, September 12, 2021, pending weather.
Phase 1 construction will be complete on August 29, 2021. This work included the reconstruction of pavement along northbound Elkton Rd, side road tie-ins, construction of a shared use path and two pedestrian bridges. On Sunday, August 29, 2021, beginning at 3 pm, northbound Elkton Road motorists will be switched to the completed northbound side of Elkton Rd. Expect delays while the traffic switch takes place. The traffic switch will be completed by 5 am on Monday, August 30, 2021. Following the traffic switch, Phase 2 Advanced work will begin and includes the installation of PCC pavement in the median and temporary asphalt pavement to maintain traffic during Phase 2 construction.